This open house was active from Oct. 21-Nov. 6, 2022. Information on this website may no longer be current. Email us for more information.
We are working on two projects to help connect sidewalks and walkways in the Aloha area:
- 188th Avenue
- 195th Avenue
Both projects include the construction of new sidewalk and a protected pedestrian crossing.
These projects are funded by the Urban Road Maintenance District (URMD). They were selected for funding based on a requests from community members, public input and selection by the Urban Road Maintenance District Advisory Committee (URMDAC).
Since 2011, 74 URMD Pedestrian and Biking Improvement Projects totaling over $39 million have been funded. The public can submit Pedestrian and Biking Improvement proposals. Eligible proposals are added to the Pedestrian and Biking Improvements Candidate List.
Timeline
-
Survey and Preliminary Design
June-October 2022 -
Open House
October 21- November 6You are here
-
Right-of-Way Acquisition
October 2022-March 2023 -
Final Design
November 2022-May 2023 -
Construction
June 2023-September 2023